How to build a video production budget

A video production budget lists every cost of making the film, grouped by phase, then adds contingency, insurance and your fee. The total cost is what the job costs you. The price is what the client pays. Keep the two apart and you will always know your margin.

By Cutvey · Published November 2, 2026 · Updated November 2, 2026

On this page
The short answerThe categoriesA worked exampleCost is not priceBudget against actualMistakes that eat the marginDoing it in Cutvey

The short answer

Build it in this order:

  1. List the days: prep, shoot and post. Days drive almost every other line.
  2. Cost each phase: pre-production, the shoot crew, talent, equipment, locations and travel, and post.
  3. Add the percent lines: payroll fringes if you employ anyone, then contingency.
  4. Add fixed overhead for the job, like production insurance.
  5. Add your production fee. That is your margin, and it is not optional.
  6. Round to a clean number and write down what the price assumes.

Then, once the job starts, track every line's actual cost against its budget. To start from a spreadsheet, use the free video production budget template.

The categories

CategoryWhat goes in it
Pre-productionProducer and director prep, scouting, casting, the script or treatment
Shoot crewDirector, director of photography, camera assistant, gaffer, grip, sound, hair and makeup, production assistants
TalentPrincipal and background talent, voiceover
EquipmentCamera, lenses, lighting and grip, sound, a drone, media and drives, expendables
Locations and travelLocation fees, permits, a studio, catering, flights, lodging, mileage, per diem
Post-productionEdit, color, sound design and mix, motion graphics, music licensing, stock
Percent linesPayroll taxes and fringes, contingency
Job overheadProduction insurance
Your feeThe production fee or markup

Commercial producers in the US often lay a bid out in the sections of the AICP bid form. A small brand film does not need every section, but the order is a good checklist.

A worked example

Here is a sample two-day brand film with one interview subject, a small crew and a five-day edit. The rates are made up for the example. Use your own and your market's.

LineSumAmount
Producer3 days at $600$1,800
Director prep1 day at $1,000$1,000
Location scout1 day$400
Pre-production$3,200
Director2 days at $1,000$2,000
Director of photography2 days at $900$1,800
Gaffer2 days at $650$1,300
Sound mixer2 days at $700$1,400
Production assistant2 days at $300$600
Shoot crew$7,100
Talent, principal2 days at $800$1,600
Camera package2 days at $600$1,200
Lighting and grip2 days at $500$1,000
Sound package2 days at $150$300
Equipment$2,500
Location feeFlat$1,500
Catering12 people, 2 days, at $35$840
Ground transportFlat$300
Locations and travel$2,640
Edit5 days at $800$4,000
Color1 day$900
Sound mix1 day$800
Music licenseOne track$400
Post-production$6,100
Direct cost$23,140
Contingency10% of direct cost$2,314
Production insuranceFor the job$750
Total cost$26,204
Production fee20% of total cost$5,241
PriceRounded$31,500

The crew here are freelancers paid on invoice, so there is no fringe line. If you put people on payroll, add payroll taxes and fringes as a percent of their wages. Ask your payroll provider for your real rate.

Two choices in this example are worth copying. Contingency is a line the client can see, so an overage has somewhere to come from. And the fee is calculated on cost, so the margin grows with the job instead of being an afterthought.

Cost is not price

CostPrice
What it isWhat the job costs youWhat the client pays
Who sees itYou and your producerThe client
Where it livesThe budgetThe proposal
What it includesEvery line, contingency, insuranceCost plus your fee, rounded, shown your way

You do not have to show the client your budget. Most small studios present a price, or a few packages, with the deliverables and assumptions written out. See how to price video production and how to write a proposal.

Budget against actual

A budget is only useful if you check it. Once the job starts, track four numbers for each line:

FigureWhat it means
BudgetWhat you planned
ActualWhat you have spent: approved expenses, crew invoices, rentals, purchase orders received or paid
CommittedWhat you have promised but not paid yet, such as an open purchase order
Estimate to completeYour honest guess at what is still to come

The estimated final cost is actual plus committed plus the estimate to complete. The variance is budget less estimated final cost.

Here is the example, after the shoot and two days into the edit:

LineBudgetActualCommittedTo completeFinalVariance
Shoot crew$7,100$7,750$0$0$7,750-$650
Equipment$2,500$2,200$0$0$2,200$300
Post-production$6,100$1,600$400$4,200$6,200-$100

The crew ran into overtime on day two, which cost $650. Equipment came in under, and post is tracking a little over. Net, the job is $450 over on these lines, well inside its $2,314 contingency. That is what contingency is for.

Mistakes that eat the margin

  • No prep days. A shoot day usually comes with prep and a load in and out.
  • Forgetting overtime. Budget a 10-hour day and say what happens past it. The crew day rate calculator works it out.
  • Post at half its real length. Count review rounds as edit days. See how many revision rounds.
  • Counting a cost twice. A rental with a purchase order and an expense for the same invoice is one cost.
  • No contingency, so every surprise comes out of your fee.
  • Never looking back. Compare the final cost with the budget on every job, and your next budget gets better.

Doing it in Cutvey

Each project's Money page has a budget. Start from a template (a commercial in the style of the AICP form, corporate video or event coverage), from the lines of the signed proposal, or from a budget you saved. Percent lines handle fringes, contingency and your fee. Actual cost fills in by itself from approved expenses, crew invoices, rentals, purchase orders, mileage and your team's time at cost, and open purchase orders show as committed. With Books in double-entry, each project also gets a cost report with an estimate to complete and the variance. See Budget a project and track its costs.

Budget the next job in Cutvey.

Start from a template, then watch actual cost fill in from the job itself. 14 days free, no card needed.